Town of Berthoud – Road Repairs

Good afternoon,

I wanted to keep all teams apprised of the updated schedule for the road repairs in Gateway Park.

8/17 – Gateway Park Blvd reopened to traffic

     – Gateway Park Dr. notified of impending work

8/18 – Lake Ave. milling

  • Gateway Park Dr. milling

8/19  – Gateway Park Dr. and Lake Ave. paved and reopened to traffic

8/20 – Glacier Ave. (Gateway Park Blvd – 14th) full reconstruction

Slurry sealing operations to follow completion of mill & overlay scope, likely to begin 8/30.

Please let me know if you have any questions or comments.

Thank you,

Daniel Buendia, PE

Project Engineer