Good afternoon,
I wanted to keep all teams apprised of the updated schedule for the road repairs in Gateway Park.
8/17 – Gateway Park Blvd reopened to traffic
– Gateway Park Dr. notified of impending work
8/18 – Lake Ave. milling
- Gateway Park Dr. milling
8/19 – Gateway Park Dr. and Lake Ave. paved and reopened to traffic
8/20 – Glacier Ave. (Gateway Park Blvd – 14th) full reconstruction
Slurry sealing operations to follow completion of mill & overlay scope, likely to begin 8/30.
Please let me know if you have any questions or comments.
Thank you,
Daniel Buendia, PE
Project Engineer
Phone: 970.344.5807
Berthoud.org 807 Mountain Ave. Berthoud, CO 80513